Phase II Steel Delivery

Posted by Pam Beaudoin on 10/13/2020 12:00:00 PM

Please be advised that our second round of steel delivery to The Manchester Memorial Elementary construction project will occur from 10/13-10/20.  Deliveries will be between the hours of 7-7:30am, and 8:30 am-2:30 pm.  The Manchester Police Department has been notified and is aware of the deliveries and will be providing detailing services.  Please see attached our trucking route traffic and logistics plan for reference.

 

Also please be advised that the construction team will be working Sunday, 10/18, from 8:00 am-4:00 pm. This is rare for us – in fact, our first time working on a Sunday for this project.  We are pushing to get this next phase enclosed before cold weather settles in.   The operations will not produce significant noise and will be mostly steel framing detailing/welding.  The work will not include any heavy machinery, i.e. cranes, etc.